“Considering the Appliance Warehouse Case Study, introduced in Week 1, and the project of planning and implementing a new Service Department as one of their product offerings. What tasks could you include in a WBS for Appliance Warehouse Case Study? What would be some possible risks for the implementation of the new Service Department?
 
Task No.      Description                                    Duration (Days)               Predecessor Tasks
1                  Reserve the meeting room           1
2                  Order the marketing materials      9
3                  Brief the managers                       2
4                  Send out customer emails            3
5                  Upload program to the app store  3
6                  Load the new software                  2
7                  Do a dress rehearsal                     1